William & Mary ISC3
Project Details
-
Williamsburg, Virginia
-
2014
Project Size
113,000 SF
Contract Amount
$11M
Customer
Whiting-Turner Contracting Company
Architect
EYP, Inc.
Engineer
EYP, Inc.
Owner
The College of William & Mary
Project Overview
This project was the construction of the Integrated Science Center Phase 3, a new 113,000 SF addition to two existing buildings, ISC1 & ISC2. The addition housed laboratory, administrative, classroom, and support spaces for the college’s science departments. Renovation work was performed on the existing ISC2 building, including placing a greenhouse on the roof and modifying the building’s facade. The work also included augmentation of the SWEM heating and cooling plant, demolition, abatement of Millington Hall, and site restoration.

Project Highlights
• 50% SWaM Participation Goal
• LEED Silver