QTS Richmond is the largest and most connected data center in the area. With access to 21+ network providers and MAREA & BUSA subsea cables terminating at this facility, it is the predominant interconnection hub in the region – enabling new, efficient, and less congested routes across the globe. ColonialWebb proudly renovated the old semiconductor manufacturing facility into a data center for QTS. The project entailed renovating a three-story, 369K SF building to become a state-of-the-art data center facility capable of housing up to 51 MW of Data Storage Capacity. ColonialWebb was selected as an early-stage design-assist partner to help facilitate the timely completion of this fast-track mission-critical renovation/conversion project.
Project Description
Project Size
- 369,414 SF
Contract Amount
- $31M
Customer
- DPR Construction
Architect
- Corgan Associates
Engineer
- kW Mission Critical Engineering
Owner
- QTS
Project Highlights
• QTY-187 CHW CRAH Units installed
• QTY-36, 490 Ton Air Cooled Chillers installed as part of this renovation project
• Total of 17,640 Tons of CHW capacity added to this existing building
• ~30,000 LF of Carbon Steel CHWS/R Piping installed on project
• Total of ~139,000 man hours on the project
• QTY-36, 490 Ton Air Cooled Chillers installed as part of this renovation project
• Total of 17,640 Tons of CHW capacity added to this existing building
• ~30,000 LF of Carbon Steel CHWS/R Piping installed on project